Frequently Asked Questions

Del Sur Elementary Remediation – Community Update (October 19, 2026)

Poway Unified is nearing completion of its investigation into the underlying causes of mold growth at Del Sur Elementary. In consultation with environmental consultants, mechanical engineers, and architects, staff is recommending additional remediation and a new heating, ventilation, and air conditioning (HVAC) system to address the campus's moisture and humidity concerns. In order to prepare for a proposed plan to install new HVAC equipment, staff will issue a request for proposals (RFP) in the coming days.

Staff and district consultants will brief the Board on conditions and recommendations at the Board's regular meeting on Thursday, November 5. At that meeting, staff will present the investigation findings, discuss the range of options possible for a permanent fix to the issue, and will request authorization to proceed with design and installation of a new system. The Board meeting will be at 6:00 p.m. in the Community Room of the District Office (15250 Avenue of Science, San Diego, 92128).

Based on what we know today, the installation of a new HVAC system at Del Sur will extend the timeline for students and staff at Stone Ranch until summer 2027; a more detailed timeline will be shared on November 5. Staff will also schedule a community information meeting for families and staff with participation from environmental, mechanical, and architectural experts in the near future. As soon as that is scheduled, we will let you know.

What has changed since the previous update?

The earlier plan focused on repairing and optimizing the existing HVAC system, improving humidity control, replacing affected finishes, and evaluating the results before reopening. At that time, the professional assessment was that the existing system could serve the campus with modifications and a consistent operating protocol. Further investigation and testing were part of that plan.

As demolition and more detailed inspections progressed, additional concerns became visible. SOCOTEC US conducted an independent mold and moisture assessment of the main building and two portable buildings between September 30 and October 8. Environmental testing reports will be finalized in the near future and will be shared as soon as they are available. The assessment identified microbial growth on chilled-water pipe insulation in portions of the first floor, water staining on pipe insulation throughout the buildings, and elevated moisture in selected mechanical closets and the maintenance room. Positively, there is no evidence of Stachybotrys chartarum, also commonly known as “black mold.”

These findings, together with the campus's history of temperature and humidity challenges, have informed the recommendation for a more extensive mechanical-system upgrade. Removing and replacing the affected insulation would address its current condition but would not, by itself, resolve the broader concern about recurring moisture.

What work has been completed?

The initial response included cleaning and antimicrobial treatment, dehumidification, air filtration, HVAC and duct cleaning, and environmental sampling. Follow-up testing identified areas requiring additional attention, leading to the relocation of students and staff while investigation and corrective work continued.

Since then, crews have removed existing flooring and selected wall and ceiling materials, moved and documented classroom contents, and supported detailed mechanical and environmental inspections. The District has engaged environmental consultants, architects, engineers, and contractors to evaluate conditions and develop the next phase of work.

What is proposed next?

The proposed work has three coordinated parts:

  • Additional removal and restoration. Remove existing chilled-water piping and insulation, classroom air-handling units, and other identified materials. Install flooring, ceiling tiles, wall panels, and other finishes with durable materials that are appropriate for school use and easier to maintain.
  • Environmental cleaning and clearance. Address identified moisture sources, clean hard surfaces and ductwork, and sanitize salvageable contents. Conduct environmental clearance testing following remediation and before reinstalling finishes.
  • A new HVAC system with humidity control. Remove the existing chilled-water cooling approach and install a refrigerant-based system. The proposed design includes new equipment serving classrooms, conditioning for interior hallways, and humidity control that removes moisture while maintaining comfortable temperatures. Rooftop equipment will require associated structural improvements.

What is the revised timeline?

The proposed schedule includes design work this fall, submission to the Division of the State Architect in December 2026-January 2027, targeted approval in February, and construction from March through June. This will be reviewed and finalized at the November 5, 2026, Board meeting. The proposed project schedule identifies July 9, 2027, as the target for building occupancy. This is a planning target and remains dependent on approvals, equipment delivery, construction, system performance, and environmental clearance.

Completion of construction alone will not determine readiness. The District will rely on professional evaluation of the completed work and environmental conditions before students and staff return. Any unresolved concerns will require further corrective work and evaluation.

How will the District continue to support both Del Sur and Stone Ranch school communities?

District staff continue to work with both principals to address the needs of Del Sur and Stone Ranch staff and students. This includes supervision, support-service space, outdoor shelter, bell schedules, staff collaboration, and additional wear on the campus; the District will also support Del Sur by ensuring that all curriculum materials and other resources are available to students and teachers. Staff will also request Board authorization for additional portable space for support services.

The District is pursuing insurance coverage and state facility hardship funding and evaluating other available funding sources. Further information about project costs and funding will be shared as the scope and estimates are refined.

We will continue to share substantive findings, finalized environmental reports, and schedule updates through school and district communications. Our commitment is to explain what we learn, how it changes the work, and what must be completed before the Del Sur community returns home.