Frequently Asked Questions

Del Sur Elementary Remediation – Community Update (November 6, 2026)

In our October 19 update, we outlined a recommendation to replace Del Sur’s HVAC system and complete additional remediation and campus restoration. At last night’s meeting, the Board of Education supported moving forward with that approach. The presentation included investigation findings, the options considered, the recommended system, and the proposed construction schedule.

The timeline remains consistent with our October update: Project completion is targeted for July 2027, with students returning to Del Sur for the start of the 2027–28 school year in August. Del Sur students and staff will continue sharing the Stone Ranch campus for the remainder of this school year.

We know this extended displacement continues to affect daily life for both school communities. We are committed to completing the work thoroughly while supporting students, families, and staff throughout the months ahead.

What did the Board review?

Staff and consultants reviewed several options, including repairing the existing system, replacing it, and establishing a larger temporary campus at Del Sur during construction. The recommendation is to remove the existing chilled-water system and install a variable refrigerant flow (VRF) system incorporating humidity control, improve ventilation and conditioning in interior corridors, and restore affected interior spaces. 

This recommendation builds on the findings shared in October. Inspections identified mold growth and water staining on chilled-water pipe insulation, along with elevated moisture in selected mechanical spaces. In some locations, pipe hangers and deteriorated insulation tape may have compromised the insulation’s protective barrier, allowing condensation to accumulate on surrounding surfaces.

Installing a new system is intended to address the broader concern about recurring moisture, along with improving classroom comfort. The recommended VRF system avoids the campuswide electrical upgrades required by the other replacement system studied and supports the July 2027 completion target. Several District locations already use VRF systems. Before finalization of the plan, staff will review updated cost projections and, if anything changes in the design recommendation before the December Board meeting, will return to the Board with that information.

What work happens next?

The project continues to involve three coordinated areas of work:

  • Removal and restoration: Complete removal of existing chilled-water piping, insulation, classroom air-handling units, and other identified materials. Install new flooring, ceilings, and wall finishes using durable materials that are easier to clean and maintain.
  • Environmental cleaning and clearance: Clean and sanitize salvageable contents for return to Del Sur staff under the supervision of our contracted industrial hygienist, complete building sanitization, and conduct environmental clearance testing before new finishes are installed.
  • HVAC replacement and humidity control: Finalize the design and install new mechanical equipment, building controls, and corridor ventilation and conditioning.

Contractor selection is underway through the lease-leaseback procurement process, with a construction contract targeted for Board consideration in December.

What is the project schedule?

The schedule presented last night includes:

  • November–December 2026: Design development and contractor selection.
  • December 2026–January 2027: Complete construction documents and submit them to the Division of the State Architect.
  • February 2027: Target state approval.
  • March–June 2027: Construction and installation.
  • July 9, 2027: Target building occupancy, allowing time to prepare for an August reopening.

These remain planning targets, dependent on approvals, equipment delivery, construction progress, system performance, and environmental clearance.

As we shared in October, completion of construction alone will not determine readiness to reopen. The District will rely on professional evaluation of the completed work and environmental conditions before students and staff return. Any unresolved concerns will require further corrective work and evaluation.

How will the District support both school communities?

District staff are working with both principals to address the needs of sharing Stone Ranch for the remainder of the school year. Priorities include supervision, support-service spaces, outdoor shelter, bell schedule considerations, staff collaboration, and the additional wear on Stone Ranch facilities. We will also continue addressing curriculum, furniture, and technology needs for staff throughout this school year.

The Board presentation included a request for additional portable classroom space at Stone Ranch to support school operations and services, and this was also approved.

What information is available to families?

The full November 5 Board presentation includes investigation findings, options considered, project milestones, and cost and funding estimates. Additional environmental and air quality testing reports are also available online.

We will share details about the community information meeting referenced in our October update once it is scheduled. We will likely schedule it after Winter Break. We will also continue to provide updates on significant findings, construction milestones, and any changes to the timeline.

Thank you to our Del Sur and Stone Ranch families and staff for your continued care for students and one another. We understand the importance of returning home with confidence in the work completed, and that remains our focus.